Evermore Estate – September 2026 Construction Update & Bank Valuations

Evermore Estate Update –

September 2026 Construction Progress

We’re pleased to share the latest construction update for Evermore Estate, Kilmore, with major infrastructure works now substantially complete and exciting milestones taking shape across the estate.

This update also includes important information regarding bank valuations and how purchasers and valuers can arrange access to the site.

Newly constructed road and footpaths at Evermore Estate, Kilmore

Bank Valuations & Site Access

We’re pleased to confirm that the September construction update announced that bank valuations could commence from early October 2026.

As Evermore Estate remains an active construction site, all bank valuations must be booked through the Projects team prior to attending. This ensures that access can be arranged safely and efficiently while the remaining construction works continue.

Bank Valuation Bookings

Contact: Martin O’Hanlon
Phone: 0484 146 656
Email: martin@hfprojects.net.au

Purchasers are encouraged to provide these contact details to their bank or appointed valuer when arranging an inspection.

Construction Progress

The September 2026 construction report confirmed that the majority of major civil works had reached 100% completion.

Completed Works – 100%
  • Vegetation clearing
  • Sewer installation
  • Drainage installation
  • Road boxing
  • Road subgrade stabilisation
  • Road rock capping layer
  • Water installation
  • Road service crossings
  • Class 3 rock to road pavement
  • Class 2 rock to road pavement
  • Electrical trenching
  • Internal electrical works
  • NBN installation

Earthworks: 95% complete as reported in September.

Latest Works on Site

With the estate roads now laid, the construction team is progressing through the final site details.

Landscaping works are underway, and the front boundary pegs for individual lots have been installed.

These milestones mark another exciting step towards completion, with the estate’s road network and individual allotments becoming increasingly recognisable.

Design Guidelines Reminder

Purchasers are reminded to submit their proposed floor plans and building drawings to the Design Review Panel for assessment.

Design Review Panel Email:
EvermoreDGs@smec.com

Looking Ahead

With major infrastructure works substantially complete and landscaping progressing, Evermore Estate continues to move closer to its next important milestones.

We’ll continue sharing construction updates, site access information and further project news as it becomes available.

If you have any questions about your block, finance, valuations or the upcoming title process, please contact the Evermore Estate team.